The following updates include demolition of the Link and renovation of the roof on Scott Engineering Center (SEC) on City Campus. These activities can be noisy, especially beginning Dec. 9.
Tear-down of the Link began Dec. 4 and is estimated to last two weeks. The building was isolated from the sides of Nebraska Hall and SEC last week. This process will include separating materials for recycling.
Earthwork will start near the end of December, including tearing out the hill by SEC and breaking up concrete surrounding the building.
The roof on SEC is being renovated with new insulation; the crew is about halfway done with this installation, due to unanticipated leaking and saturated old insulation. This project is estimated for completion by the end of December.
The SEC north stair tower will also be removed this month.
Project managers are aware of the Finals class schedule and will work as possible to accommodate these times and minimize noise disruptions.
As a reminder, visitors are not allowed within the construction site without permission from Hausmann Construction or the project managers. If within the fenced-in areas, safety guidelines must be followed (see sign).
More details at: https://engineering.unl.edu/construction-central/