“High Availability” project continues, network outage, August 3

Phase 3 in preparation of increasing network capacity to a 100 gigabit, high redundancy environment.
Phase 3 in preparation of increasing network capacity to a 100 gigabit, high redundancy environment.

The third phase of a "high availability" upgrade to the campus network will result in a network outage to a number of City Campus buildings on Sunday, August 3 from 8:00 a.m. to 12:00 p.m. The work is in preparation of creating a higher capacity, more fully redundant network environment.

Information Technology Services will install an additional distribution router that will increase bandwidth and redundancy to campus buildings. This is the third in a series of network distribution upgrades initiated on May 11. By the end of the summer, bandwidth to all City campus locations will double to 2 gigabits. Additional project phases will continue on both City and East campuses through next year.

By the end of 2015, UNL will increase its internet capacity through commodity vendors and connections to consortiums Internet2 and OmniPop.

All wired and wireless networking in these locations will be affected by this work unless noted otherwise.  Administrative access to the following services will be impacted, but most of the following services will continue to function: Energy Management (EMCS), CCTV, Alarms, Door Access. (See end of article for other locations and services, including the SEC Datacenter that are partially affected).
 
1000 N 22
1111 Lincoln Mall (University Press)
14th & Avery Parking Garage
1520 North 20th Circle (Office of Online & Distance Education)
17&R Parking Garage (UNL Police)
1740 Vine (American Math Competitions)
19th & Vine Parking Garage
Architecture Studio – Haymarket
Beadle Center
Benton Hall
Business Services Complex
Center on Children, Families, and the Law
Coliseum
Devaney Sports Center/Hendricks
Facilities Management & Planning
Facilities Management Shops
Fairfield Hall
Henzlik Hall
Jorgensen Hall
Landscape Services
LTAP
Mabel Lee Hall
Military & Naval
Nebraska Hall (CSN not affected)
Othmer Hall
Outdoor Adventures Center
Sapp Recreation Facility (CREC)
Scott Engineering Center
•             includes SEC Link, all Labs and Office areas
•             Also includes ITS offices & Call Center in basement
•             For SEC Datacenter, see specific section below
Seaton Hall
Teachers College Hall
Track Office Building
Transportation Services
University Health Center
University Housing Office
Utility Plant
Whittier Research Center
 
 
The following campus locations will be partially impacted:
 
Residence Halls
 
-Resnet network connections will NOT be affected.
-City campus residence halls - ALL non-Resnet network connections will be affected (ex. Housing Admin network, CCTV, door access, Energy Management, networked alarms).
-East campus residence halls - The Housing Admin network will be affected (other services such as CCTV, door access, Energy Management, networked alarms will NOT be affected).
-Housing Datacenters in Schramm & Selleck will be affected.
 
Memorial Stadium
-All wireless networking for West, East, North Stadium & Hawks Championship Center will be affected.
 
 
Virtual Private Network (VPN):
 
-The primary UNL VPN concentrator will be affected; however no VPN outage is expected as services will failover to the secondary concentrator.
 
Impact on SEC 29 Datacenter:
(Note: The work below affecting the SEC Datacenter is anticipated to be limited to the 8am-8:30am timeframe)
 
Impacted IP ranges for servers have been previously communicated to Data Center occupants.